Removing the Mixture
- close valve 13A, open valves 9 and 3
- set the mixing chamber heater and the still heater to 20 mW
- the VTI set temperature can be set to 10 K, as soon as the dump
pressure is beyond 90 % of its original value (630 mbar on DIL?
500 mbar on DIL2)
- wait until the pressure on P1 drops below 0.01 mbar (or 0.1 mbar,
if the stick is used again), then close all valves.
This particular version was published on 02-Jul-2007 14:22:28 UTC by MarkusZolliker.
|
|