Difference between version 21 and version 5:
At line 2 added 9 lines.
+ It is highly recommended to use the automatic condensing scripts in SEA.
+ Click on "sorbpump", when "readyforpump", make sure that the IVC is connected
+ to a running turbo pump, and the valve and the IVC space is open.
+
+ The automatic script is doing a sligthly different condensing procedure than
+ described below.
+
+ * If not yet done, the IVC has to be pumped. Do not do that before the sorb T
+ is at 4K.
Lines 6-25 were replaced by lines 15-19
-
- * On the Variox or Magnet VTI, open the needle valve more than
- usual in order to fill the pumping volume with some
- amount of liquid helium. Put a "flow" of 20 mbar until the
- 1 K pot temperature is stable below 3 K. Then close
- the needle valve until a "flow" of about 10 mbar is reached
- (this takes some time, as the pressure decreases only slowly).
- Then regulate the valve at about 8 mbar. This value must not
- be obeyed exactly. In principle, the best needle valve setting
- is reached, when the 1 K pot temperature (not the VTI temperature!)
- is minimal. Hours might be spend to optimize the
- needle valve opening, a better idea is take somthing between 8 and
- 10 mbar as a good starting point, and optimize later, if necessary.
- It should be possible to achieve a 1 K pot temperature of
- about 2 K with the Variox and about 2.5 K with the MA09.
- However, when condensing the mixture, the 1 K pot temperature
- might increase to 3 to 4 K for a short time, when pushing the
- mixture quickly.
-
- * Open the 3 valves in the pumping line and the 2 valves in
+ * Cool the VTI ("1 K pot" thermometer) to a temperature below 3 K. With the
+ Variox 2 K may be reached, with MA09 about 2.5 K.
+ Open the needle valve to get a pressure at the 65 m3
+ pump of about 12 mbar.
+ * Open the valves in the pumping line and in
Line 27 was replaced by line 21
- * Open the green valve marked "out" below the dump. The dump is the
+ * Open the green valves marked "out" and "in" on the dump. The dump is the
Lines 30-34 were replaced by lines 24-30
- RAISE).
- * Open valve 9 (while pressing on the valve button, press
- RAISE).
- * The reading on G2 is proportional to the amout of mixture in the
- dump. It should read something around 660 mbar.
+ RAISE).
+ * Make sure that the heater on the mixing chamber is off and that
+ the setpoint is zero. Switch off the still heater also.
+ * Open valve 9 (while pressing on the valve button, press
+ RAISE).
+ * The reading on G2 is proportional to the amount of mixture in the
+ dump. It should read something around 660(DIL1) or 400(DIL2) mbar.
Lines 37-47 were replaced by lines 33-48
- * Open a little valve 12A (4.0 % to start).
- * While the pressure reading on G1 should always be below about 400 mbar,
- Valve 12A can bae opened gradually, and opened completely, when the
- reading on G2 drops below 350 mbar.
-
- * After some time (about 30 min when using the Variox) the pressure on
- G1 falls below 150 mbar, and it is time to pump out the dump: close
- valve 9, and open valve 14 for a short time (close it when P1 raises
- above 50 mbar). As soon as the pressure on P1 drops down, you might open
- and close valve 14 again, but make sure that the pressure on G1 does
- not increase above 350 mbar.
+ * Open valve 13A
+ * Open V12A a little (4 %) to allow the mixture pass the trap slowly.
+ * When the pressure reading on G1 stabilizes or decreases, open valve 12A
+ completely.
+ * During condensation, the 1 K pot temperature might raise to more than 3 K,
+ especially when the pressure on G1 is high. Adjusting the needle valve
+ is only necessary, when this temperature get too high and prevents
+ the condensation to progress.
+ * After some time (depends on the temperature of the mix. chamber)
+ the mixing chamber should reach about 1 K, and then
+ the pressure on G1 stabilizes at a low value.
+ Now you may start to pump out the dump: close valve 9,
+ and open valve 14 for a short time
+ (close it when P1 raises above 50 mbar).
+ As soon as the pressure on P1 drops down, you might open
+ and close valve 14 again. Do that several times.
Line 49 was replaced by line 50
- raise above 50 mbar. Leave the valve open until the P1 drops below 0.1.
+ raise above 50 mbar. Leave the valve open until P1 drops below 1.
Removed line 55
-
Lines 57-58 were replaced by lines 57-58
- the flow on the condenser line might falls below 100 (black display below
- the valve panel).
+ the flow on the condenser line might fall below 100 (black display below
+ the valve panel, on DIL1 only).
At line 60 added 2 lines.
+
+ [DIL1/igh.png]

Back to CondenseMixtureDIL, or to the Page History.